NEW QUESTION 10
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.
What should the program manager update first?
- A. Benefits management plan
- B. Procurement management plan
- C. Benefits register
- D. Risk register
Answer: C
NEW QUESTION 11
The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system. What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
NEW QUESTION 12
What is the MINIMUM lighting requirement (or telecommunications spaces?
- A. 500 lux (46 foot-candles) of lighting in the horizontal plane and 500 lux (46 foot-candles) of lighting in the vertical plane measured at at 1 meter (3 28 feet) above the finished floor
- B. 50 lux (4.6 toot-candles) of lighting in the horizontal plane and 20 lux (1.9 fool-candles) of lighting in the vertical plane measured al at 1 meter (3.28 feet) above the finished floor
- C. 500 lux (46 foot-candles) of lighting in the horizontal plane and 200 lux (18 6 foot-candles) of lighting in the vertical plane measured at at 1 meter (3 28 feet) above the finished floor
- D. 200 lux (18 6 fool-candles) of lighting In the horizontal plane and 500 lux (46 foot-candles) of lighting In the vertical plane measured at at 1 meter (3.28 feet) above the finished floor
Answer: C
NEW QUESTION 13
Which of the following is TRUE about convenience receptacles?
- A. They are those into which equipment, such as switches, shall be plugged
- B. They must be powered by emergency power to prevent loss of service.
- C. They increase the count of outlets needed on the equipment racks.
- D. They shall be connected to occupancy sensors to ensure user safety.
- E. They are duplex or quad receptacles mounted on perimeter walls.
Answer: E
NEW QUESTION 14
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years What is the expected time of delivery?
- A. 175 years
- B. 1 50 years
- C. 1 00 years
- D. 1.25 years
Answer: D
NEW QUESTION 15
An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft). How many supports will be needed''
- A. 0
- B. 1
- C. 2
- D. 3
- E. 4
Answer: C
NEW QUESTION 16
A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).
What should the program manager update?
- A. Program communications management plan
- B. Benefits management plan
- C. Stakeholder engagement plan
- D. Benefits transition plan
Answer: B
NEW QUESTION 17
A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program As a result, the program manager must do which of the following'?
- A. Apply resource leveling considering the constraints of time, budget, and quality
- B. Assign the tasks on the critical path to the resources available to adhere to the project schedule
- C. Delay the start of the program until the assigned resources are available
- D. Utilize team members that are currently available, even though they do not have the expertise needed.
Answer: B
NEW QUESTION 18
Which of the following is a consideration for lighting telecommunication spaces?
- A. To ensure worker safety within TEs. Light level requirements are higher tor these than other spaces
- B. The electrical power for lighting shall be connected to the same electrical panel as the telecommunications equipment.
- C. The light fixtures within telecommunications spaces shall be fluorescent type fixtures.
- D. The lighting layout shall be coordinated with the equipment and pathway locations
Answer: D
NEW QUESTION 19
A voice over IP network that converges voice capabilities with softphones. Video communications, instant messaging is referred to as
- A. Ethernet network communications
- B. unified communications.
- C. mesh communications services
- D. converged communications
- E. unified fabric architecture
Answer: B
NEW QUESTION 20
A new program is comprised of four component projects. The program manager must assign project managers to each of the tour projects. There are eight potential project managers to consider. What should the program manager do before assigning the project managers?
- A. Determine budgetary constraints related to the project managers' salaries
- B. Interview each project manager to determine their career aspirations
- C. Evaluate the project managers' skills and match them to the needs of the projects
- D. Request performance feedback from the project managers' line managers
Answer: C
NEW QUESTION 21
A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
- A. Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered
- B. Host a kick-off meeting, request preliminary requirements from the marketing department, conduct a design session present the steering committee with a solution that meets the requirements: and meet with interested vendors
- C. Ask a senior marketing executive to act as the program sponsor and participate on the steering committee: require steering committee representation from the IT legal, and other key departments, validate that the chosen solution meets the requirements
- D. Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gam the confidence of the legal department
Answer: B
NEW QUESTION 22
Exhibit:
A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (American with Disabilities Act) requirement for front reach using a wheelchair. What will be the maximum reachable height or the value of "X"?
- A. 1220 mm (48 in)
- B. 864 mm (34 in)
- C. 1170 mm (46 in)
- D. 760 mm (30 in)
- E. 1370 mm (54 in)
Answer: A
NEW QUESTION 23
Stakeholders ask the program manager to assess reasons for the project's delay and provide a report also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget The program manager distributes information in accordance with which of the following?
- A. Communications management plan
- B. Stakeholder engagement plan
- C. Program governance charter
- D. Schedule management plan
Answer: A
NEW QUESTION 24
The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.
What should the program manager do next?
- A. Avoid known critical project threats.
- B. Perform a final review of project scope
- C. Establish a contingency reserve
- D. Transfer a percentage of known risks
Answer: C
NEW QUESTION 25
Which of the following is TRUE for tele communications spaces?
- A. Relative humidity snail be maintained at 40% ± 5%.
- B. Plumbing piping not related to the support of the space should not pass through the space.
- C. Maintain aim (3.28 ft) clearance between equipment and plumbing fixtures such as mop sinks
- D. Close proximity to water service is desired so consider locating the ER in the pipe chase.
Answer: B
NEW QUESTION 26
Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?
- A. Mutual drainage reactors
- B. Isolating transformers
- C. 2-winding neutralizing transformers
- D. Unit-type neutralizing transformers
- E. Neutralizing transformers
Answer: B
NEW QUESTION 27
Which of the following two items are examples of items associated with a submittal? (Select two options.)
- A. Punch List
- B. Product Data
- C. Request tor permits
- D. Shop Drawings
- E. As-built
Answer: B,D
NEW QUESTION 28
A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects.
Where should the program manager incorporate this input?
- A. Stakeholder register
- B. Vendor management matrix
- C. Program risk management plan
- D. Program management plan
Answer: D
NEW QUESTION 29
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?
- A. Degradation of program communications
- B. Slow down in program implementation
- C. Reduction in program quality
- D. Reduction in program risk
Answer: B
NEW QUESTION 30
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk What should the program manager do to monitor and control the supplier?
- A. Examine performance reports, audits, and inspections
- B. Use expert judgment and update the program procurement plan
- C. Review proposal evaluation criteria, risk analyses, and mitigation strategies
- D. Seek stakeholder approval of program procurement management activities
Answer: A
NEW QUESTION 31
Open RFI's should be reviewed on a _________basis.
- A. daily
- B. weekly
- C. bi-monthly
- D. bi-weekly
Answer: B
NEW QUESTION 32
When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in a cable tray?
- A. There is no fill ratio for cable tray
- B. 50 percent
- C. 40 percent
- D. 20 percent
Answer: C
NEW QUESTION 33
For optical fiber cabling, which of the following test instruments is used to locate and identify any anomalies?
- A. OTDR
- B. OLTS
- C. Optical power meter
- D. Spectrum analyzer
Answer: A
NEW QUESTION 34
......