NEW QUESTION # 40
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Basic dates of the network activity
  • B. Basic dates of the WBS
  • C. Forecast dates of the WBS
  • D. Actual dates of the network activity

Answer: A

Explanation:
To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. The requirement date for a material component is derived from the basic start date of the activity to which it is assigned. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 41
Which object is relevant in assembly processing to create an assembly order for the SD document?

  • A. Control key
  • B. Requirement class
  • C. Item category
  • D. Project profile

Answer: D


NEW QUESTION # 42
Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

  • A. Production orders assigned to WBS elements
  • B. Maintenance orders assigned to an activity
  • C. Project-relevant purchase orders
  • D. Capacity requirements

Answer: B,D

Explanation:
The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002


NEW QUESTION # 43
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.

  • A. Controlling area
  • B. Planning department
  • C. Plant
  • D. Company code

Answer: A


NEW QUESTION # 44
What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to this question

  • A. Project simulations can be used to plan structures and costs
  • B. Project simulations can create purchase requisitions
  • C. Multiple project simulations can be used simultaneously
  • D. Project simulations can be created without using an operational project as a template
  • E. Project simulations allow posting of actual data

Answer: A,C,D

Explanation:
Project simulations are some of the advantages of using project simulations in SAP Project System. Project simulations are copies of projects that allow you to plan and simulate different scenarios without affecting operational projects. Project simulations can be created without using an operational project as a template, which means you can start from scratch or use a standard structure. Project simulations can be used to plan structures and costs, which means you can create and change WBS elements, networks, activities, and cost elements. Multiple project simulations can be used simultaneously, which means you can compare different alternatives and choose the best one. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 45
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

  • A. Usage of cost elements is mandatory
  • B. Sales prices are maintained in the DIP profile
  • C. Sources can be based on line items
  • D. Material determination is mandatory
  • E. DIP is used to create a quotation

Answer: B,C,D

Explanation:
Dynamic item processor (DIP) is a tool that allows you to create sales order items automatically based on project data. Some of the features of DIP are: Sales prices are maintained in the DIP profile, which is a parameter that defines how sales order items are created and priced from project data. Sources can be based on line items, which means that you can use individual cost elements or revenue elements as sources for creating sales order items. Material determination is mandatory, which means that you have to assign a material number to each source in order to create sales order items. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 46
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

  • A. In the project type
  • B. In the project definition of a standard WBS
  • C. In the project version
  • D. In the operative WBS element
  • E. In the project profile

Answer: A,D,E

Explanation:
User status profiles are used to define additional statuses for project objects that can control their business processes. You can assign user status profiles for WBS elements in the project profile, which is a template for creating projects with similar characteristics. You can also assign user status profiles for WBS elements in the project type, which is a classification of projects according to their objectives and characteristics. You can also assign user status profiles for WBS elements in the operative WBS element itself, which is a structural element of a project that represents a task or a partial task. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 47
How can you confirm the working hours of different work centers for a single activity?

  • A. Assign multiple work centers to the activity.
  • B. Enter multiple work centers within a single confirmation.
  • C. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.
  • D. Enter direct activity allocation assigning multiple work centers.

Answer: D


NEW QUESTION # 48
The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

  • A. Activity allocation
  • B. Calculation of actual values
  • C. Creation of purchase orders
  • D. Goods receipt for purchase order

Answer: C


NEW QUESTION # 49
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. The system automatically creates a new purchase requisition with the difference to the original quantity
  • B. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)
  • C. The purchase order is updated automatically to match the new quantity while saving the project.
  • D. A workflow can be triggered to inform the purchasing group.

Answer: C


NEW QUESTION # 50
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.

  • A. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
  • B. The material master is set to external procurement.
  • C. The material is assigned to the activity as a non-stock material.
  • D. The availability check for material components indicates missing parts.

Answer: A,D


NEW QUESTION # 51
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.

  • A. By searching via status selection profile
  • B. By searching via status combination code
  • C. By searching for the status profile
  • D. By searching for the individual status

Answer: C,D


NEW QUESTION # 52
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

  • A. If the reduction strategy is set in each activity
  • B. If the appropriate reduction type is set in the parameters for network scheduling
  • C. If the reduction strategy is set in the network header
  • D. If the maximum reduction level is less than 100

Answer: B,D


NEW QUESTION # 53
What could be a reason to use expert mode in the valuation method for results analysis?

  • A. Usage of different line ID
  • B. Assignments of different accounts for postings to financial accounting
  • C. Billing WBS elements belonging to different company codes
  • D. Valuation in different currencies

Answer: C


NEW QUESTION # 54
What are the prerequisites for resource-related billing? Note: There are 2 correct answers to this question

  • A. Released WBS elements, activities, and/or activity elements
  • B. An activity-account-assigned network that is assigned to a sales order item
  • C. A dynamic item processor (DIP) profile with the appropriate settings
  • D. A header-account-assigned network that is assigned to a sales order item

Answer: B,C

Explanation:
The prerequisites for resource-related billing are a dynamic item processor (DIP) profile with the appropriate settings and an activity-account-assigned network that is assigned to a sales order item. Resource-related billing is a process that allows you to bill customer-specific services based on individual materials, internal activities, and costs. The prerequisites for resource-related billing are:
A dynamic item processor (DIP) profile with the appropriate settings: A DIP profile is a parameter that defines how billing requests are created from project data, such as activities, materials, PRTs, and so on. A DIP profile contains various settings, such as which data sources are used, how prices are determined, how quantities are calculated, and so on. You have to create and maintain DIP profiles in Customizing for Project System under Revenues and Earnings Integration with SD Documents Dynamic Item Processor .
An activity-account-assigned network that is assigned to a sales order item: An activity-account-assigned network is a network that has its activities assigned to different account assignments, such as cost centers, orders, or sales orders. An activity-account-assigned network that is assigned to a sales order item means that some or all of its activities are assigned to an item of an SD document (such as standard order) with controlling object. This enables costs and revenues to be updated in both the SD document and the controlling object.


NEW QUESTION # 55
How can you record external service activities with service master data? Note: There are 2 correct answers to this question

  • A. Post a goods receipt in the goods movement application (MIGO)
  • B. Create a service entry sheet
  • C. Confirm the activities in the Cross-Application Time Sheet (CATS)
  • D. Confirm the network activity for external service

Answer: A,D


NEW QUESTION # 56
Which report can use user-specific layouts?

  • A. Line item report
  • B. Hierarchical report
  • C. Cost element report
  • D. Enhanced individual overview

Answer: A


NEW QUESTION # 57
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

  • A. Actual revenue is posted via a billing plan assigned to a WBS element
  • B. Actual revenue is posted via a billing document created from a sales order
  • C. Planned revenue can be transferred from a sales quotation
  • D. Planned revenue requires a sales order assigned to a WBS element

Answer: A,C


NEW QUESTION # 58
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

  • A. Requirements type
  • B. Requirements class
  • C. Item category
  • D. Schedule line category

Answer: C

Explanation:
The item category is the customizing object that controls the billing of sales order items for a customer project. The item category is a parameter that defines the basic characteristics and functions of a sales order item, such as whether it is relevant for billing or not, whether it requires a delivery or not, and whether it can be invoiced individually or collectively. The item category also determines which billing plan type can be used for a sales order item. The billing plan type is a parameter that defines how billing dates are determined and how billing amounts are calculated for a sales order item. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 59
To which object can you assign a factory calendar?

  • A. Network header
  • B. Milestone
  • C. Material component
  • D. Relationship

Answer: A

Explanation:
To assign a factory calendar, you can use the network header. The network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. The network header also contains the factory calendar field, which allows you to assign a factory calendar to a network. A factory calendar is a parameter that defines the working days and holidays for a plant or a location. A factory calendar is used to determine the dates and durations of activities and networks based on their workdays and non-workdays. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 60
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.

  • A. Basic dates
  • B. Baseline dates
  • C. Forecast dates
  • D. Planned dates

Answer: A,C


NEW QUESTION # 61
Project Structure
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note : there are 3 correct answer for this question.

  • A. The WBS structure can contain several level 1 WBS element, (es configurable por perfil de proyecto)
  • B. You can create several WBS elements per level.
  • C. A new work breakdown structure must contain up to 10 levels.
  • D. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
  • E. A WBS element of the new project can be assigned to a different project definition.

Answer: A,B,D


NEW QUESTION # 62
COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?

  • A. Cost forecast
  • B. Availability control
  • C. Easy cost planning
  • D. Results analysis

Answer: B


NEW QUESTION # 63
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Settlement rule
  • B. Results analysis key
  • C. Costing sheet
  • D. Investment profile

Answer: C


NEW QUESTION # 64
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

  • A. The table of MRP controllers
  • B. The control key
  • C. The scheduling parameters for the network
  • D. The network profile

Answer: C


NEW QUESTION # 65
......


Earning the SAP Certified Application Associate - SAP S/4HANA Project Systems certification can open up new career opportunities for professionals in the project management field. It demonstrates to potential employers that the candidate has a deep understanding of project management concepts and can effectively use SAP S/4HANA Project Systems to manage complex projects. Overall, the SAP C_TS412_2021 exam is an excellent way for project management professionals to validate their skills and advance their careers.


To prepare for the SAP C-TS412-2021 exam, candidates should have a good understanding of SAP S/4HANA Project Systems, as well as experience with project management and accounting. SAP offers a variety of training courses and learning resources, including online courses, virtual classroom training, and self-study materials. Candidates can also take advantage of practice exams and study guides to help them prepare for the exam.

 

REAL C_TS412_2021 Exam Questions With 100% Refund Guarantee : https://passking.actualtorrent.com/C_TS412_2021-exam-guide-torrent.html